Penny Place Apartments Construction Update for October 2020.

Maxcon completed the full structure and façade to Level 23 during October 2020.

While fitout progress includes:

  • Level 23 Window installation commenced
  • Level 23 Balustrade & A/C boxes installed
  • Level 22 Plaster complete
  • Level 20 Joinery installed
  • Level 21 Services (rough-in) complete
  • Level 18 Services 2nd fix complete
  • Level 17 Splash backs installed
  • Level 17 Tiling complete
  • Level 17 Stone installed
  • Level 16 FFE installed
  • Level 14 Bins Chutes installed

Maxcon are still on track for completion Q2 2021 with move-in from early Q2 2021.